110 unit Apartments, undergoing exterior renovations

Private Owners

In Newton, MA, the Owners are currently proceeding with a 45-year refresh including new roofs, elevators, balcony decks, and more.

Here, we evaluated the opportunity to install EV charging facilities prior to paving.  Eight charging stations will be available at the project's completion, with sixteen additional stations pre-wired and available when needed.

During this process, we discovered the transformers and underground wiring needed to be replaced, pushing us to postpone the new pavement.

Ultimately, the exploration of the new charging facilities avoided the likely excavation of a new parking lot, and will provide occupants plenty of capacity into the foreseeable future.